Arnold, CA…CCWD Construction Update: July 17-21: Construction crews will be testing recently installed pipeline on Blagen Road and tying the new section of pipeline into the main system, which could cause minor traffic delays in the area. Additional work will take place near the District’s Sawmill Tank on the hill above White Pines Lake, but that work is not expected to have any impact on the public. On July 20, work is expected to begin on the trenching and installation of new pipeline near the cabinet shop at the corner of Willow Street and Sequoia Road heading toward Cedar Center.
July 23-28: Work will continue to work on pipeline installation near the cabinet shop on Willow Street through July 23. From July 24-28, crews will be trenching and installing new pipeline in the Cedar Center area. Large equipment and construction activity will create traffic delays in the area, and some businesses will be impacted by this work. CCWD is notifying businesses in the area of this upcoming work.
Project summary
As of July, T&S Construction had replaced about 16,000 feet of pipeline and another 3,000 feet remain, and the project is about 85 percent finished. The remaining portions of pipeline that need to be replaced are from Pine Drive through Oak Court and Cedar Center to Sequoia Street. Substantial completion of the project is expected in August 2017.