Caltrans Weekly Road Report Through July 18

Stockton, CA…The latest and greatest road report to keep you abreast of all the upcoming Caltrans repairs and delays in our area now that summer weather is here for repairs and construction. The complete report is enclosed….

4 ALP 26.1 31.7 07/13/15 07/17/15 8:30 18:01 EB/WB Begin: Silver Creek
End: State Route 89
Restriction: One-way traffic control
Reason: Drainage Cleaning
10 mins
4 SJ 8.2 14.3 07/12/15 07/17/15 20:01 5:01 EB/WB Begin: Bacon Island Road / Trapper Road
End: Cordes Ranch Road (Left)
Restriction: One-way traffic control
Reason: Miscellaneous Work
10 mins
4 SJ 8.2 14.3 07/13/15 07/17/15 7:01 16:01 EB/WB Begin: Bacon Island Road / Trapper Road
End: Cordes Ranch Road
Restriction: Right shoulder
Reason: Miscellaneous Work
NONE
4 SJ 19.4 19.4 07/13/15 07/17/15 22:01 3:01 SB Begin: State Route 4/Crosstown Freeway
End: State Route 4/Crosstown Freeway
Restriction: Full connector ramp closure
Reason: Highway Construction
10 mins
4 SJ 19.8 20.2 07/13/15 07/17/15 21:01 5:01 EB/WB Begin: Farmington Rd
End: Farmington Rd
Restriction: One-way traffic control
Reason: Roadway Excavation
10 mins
4 SJ 20.2 20.2 05/27/15 07/17/15 7:01 17:30 EB Begin: Sinclair Ave
End: Sinclair Ave
Restriction: Long-term right shoulder
Reason: Curb/Gutter/Sidewalk Work
NONE
5 MER 32.1 32.5 07/13/15 07/17/15 7:01 16:01 NB/SB Begin: Garzaz Creek Bridge
End: Merced/Stanislaus County Line
Restriction: Right shoulder, left shoulder
Reason: Shoulder Work
NONE
5 MER 32.5 32.5 07/12/15 07/17/15 19:01 5:01 NB/SB Begin: State Route 140
End: State Route 140
Restriction: Full on and off-ramp closure
Reason: Pavement Repair
10 mins
5 MER 32.5 32.5 07/12/15 07/17/15 20:01 7:01 NB/SB Begin: Garzaz Creek Bridge
End: Merced/Stanislaus County Line
Restriction: #1 of 2 lanes
Reason: Pavement Repair
10 mins
5 SJ 0 12.4 07/12/15 07/17/15 19:01 6:01 NB/SB Begin: Stanislaus/San Joaquin County Line
End: Tom Paine Slough
Restriction: #1, #2 of 2 lanes
Reason: Pavement Repair
10 mins
5 SJ 0.7 12.4 07/13/15 07/17/15 7:01 16:01 NB/SB Begin: Stanislaus/San Joaquin County Line
End: Tom Paine Slough
Restriction: Shoulder closure
Reason: Pavement Repair
NONE
5 SJ 3.4 3.4 07/12/15 07/17/15 20:01 6:01 NB/SB Begin: State Route 132
End: State Route 132
Restriction: Various full connector ramp closure
Reason: Pavement Repair
10 mins
5 SJ 6.5 6.5 07/12/15 07/17/15 21:01 6:01 NB/SB Begin: State Route 33
End: State Route 33
Restriction: Various Full connector ramp closure
Reason: Pavement Repair
10 mins
5 SJ 6.5 6.5 07/12/15 07/17/15 19:01 4:01 SB Begin: State Route 33
End: State Route 33
Restriction: #1 of 2 lanes
Reason: Bridge Work
10 mins
5 SJ 6.5 6.5 07/12/15 07/17/15 19:01 4:01 SB Begin: State Route 33
End: State Route 33
Restriction: Full on-ramp closure
Reason: Bridge Work
10 mins
5 SJ 11.1 11.1 07/12/15 07/17/15 19:01 6:01 NB/SB Begin: Kasson Road
End: Kasson Road
Restriction: Full on and off-ramp closure
Reason: Pavement Repair
10 mins
5 SJ 11.1 11.1 07/12/15 07/17/15 19:01 6:01 SB Begin: Kasson Road Over-Crossing
End: Kasson Road Over-Crossing
Restriction: Full of/on ramp closure
Reason: Pavement Repair
10 mins
5 SJ 11.8 11.8 07/12/15 07/17/15 20:01 6:01 NB/SB Begin: 11th Street
End: 11th Street
Restriction: Full on and off-ramp closure
Reason: Pavement Repair
10 mins
5 SJ 11.8 11.8 07/12/15 07/17/15 21:01 6:01 NB Begin: 11th Street Over-Crossing
End: 11th Street Over-Crossing
Restriction: Full on ramp closure
Reason: Pavement Repair
10 mins
5 SJ 12.4 14.5 07/17/15 07/17/15 7:01 13:01 NB/SB Begin: Tom Paine Slough
End: San Joaquin River
Restriction: Moving closure – #1 of 5 lanes, median, left shoulder
Reason: Sweeping Operation
NONE
5 SJ 14.1 25.4 07/13/15 07/16/15 8:30 14:30 NB/SB Begin: Mossdale Road
End: State Route 4/Charter Way
Restriction: Intermittent #1, #3 of 3 lanes, auxiliary lane, left shoulder
Reason: Sweeping Operation
5 mins
5 SJ 21.4 21.4 07/12/15 07/17/15 22:01 6:01 NB Begin: Mathews Road
End: Mathews Road
Restriction: #2, #1 of 3 lanes
Reason: Bridge Work
10 mins
5 SJ 25.4 28.5 07/12/15 07/17/15 21:01 5:01 NB/SB Begin: State Route 4/Charter Way
End: Country Club Boulevard
Restriction: #3, #2, #1 of 3 lanes
Reason: Highway Construction
10 mins
5 SJ 26.1 26.1 07/12/15 07/17/15 22:01 5:01 NB/SB Begin: State Route 4/Crosstown Freeway
End: State Route 4/ Crosstown Freeway
Restriction: Full connector ramp closure
Reason: Highway Construction
10 mins
5 SJ 28.5 28.5 07/12/15 07/17/15 21:01 5:01 NB/SB Begin: Country club Boulevard
End: Country Club Boulevard
Restriction: Full on and off-ramp closure
Reason: Highway Construction
10 mins
5 SJ 28.5 32.7 07/15/15 07/17/15 20:01 6:01 NB Begin: Country Club Boulevard
End: Hammer Lane
Restriction: #3, #1 of 3 lanes
Reason: Sign Work
10 mins
5 SJ 39.6 39.6 07/12/15 07/17/15 20:01 5:01 NB/SB Begin: State Route 12
End: State Route 12
Restriction: various full connector ramp closure
Reason: Paving Operation
10 mins
5 SJ 39.6 39.6 07/12/15 07/17/15 20:01 5:01 NB/SB Begin: State Route 12
End: State Route 12
Restriction: #3 of 3 lanes
Reason: Paving Operation
5 mins
5 SJ 49.2 49.2 07/12/15 07/17/15 21:01 5:01 SB Begin: Barber Road
End: Barber Road
Restriction: #1 of 2 lanes
Reason: Bridge Work
10 mins
5 STA 0 28.1 07/12/15 07/17/15 20:01 5:01 NB Begin: Merced/Stanislaus County Line, Route 140
End: Stanislaus/San Joaquin County Line
Restriction: #1, #2 of 2 lanes
Reason: Pavement Repair
10 mins
5 STA 0 28.1 07/12/15 07/17/15 7:01 16:01 NB/SB Begin: Merced/Stanislaus County Line
End: Stanislaus/San Joaquin County Line
Restriction: Shoulder work
Reason: Misc work
5 mins
5 STA 5.5 5.5 07/12/15 07/17/15 20:01 6:01 NB/SB Begin: Stuhr Road
End: Stuhr Road
Restriction: Full on and off-ramp closure
Reason: Pavement Repair
10 mins
5 STA 5.5 5.5 07/12/15 07/17/15 21:01 5:01 NB Begin: Stuhr Road Over-Crossing
End: Stuhr Road Over-Crossing
Restriction: Full off/on ramp closure
Reason: Pavement Repair
10 mins
5 STA 20.7 20.7 07/13/15 07/13/15 9:01 11:30 NB Begin: Kern Creek Road
End: Kern Creek Road
Restriction: #1 of 2 lanes
Reason: Bridge Work
5 mins
5 STA 20.7 20.7 07/13/15 07/17/15 12:01 14:30 SB Begin: Kern Creek Road
End: Kern Creek Road
Restriction: #1 of 2 lanes
Reason: Bridge Work
5 mins
5 STA 23 23 07/12/15 07/17/15 21:01 5:01 NB Begin: Ingram Creek-Westley/Howard
End: Ingram Creek Westley/Howard
Restriction: Full off- ramp closure
Reason: Pavement Repair
10 mins
5 STA 27.2 27.2 07/12/15 07/17/15 19:01 6:01 NB/SB Begin: Westley Rest Area
End: Westley Rest Area
Restriction: Full on and off-ramp closure
Reason: Pavement Repair
10 mins
5 STA 27.2 27.2 07/12/15 07/17/15 20:01 5:01 NB Begin: Westley Rest Area, West
End: Westley Rest Area, West
Restriction: Full off/on ramp closure
Reason: Pavement Repair
10 mins
12 CAL 9.7 10.2 06/22/15 10/09/15 7:01 6:59 EB/WB Begin: Pine Street
End: Cosgrove Creek
Restriction: Long-term right shoulder
Reason: Highway Construction
NONE
12 CAL 9.8 10.3 07/13/15 07/17/15 7:01 17:01 EB/WB Begin: Pine Street
End: Cosgrove Creek
Restriction: One-way traffic control
Reason: Utility Work
5 mins
12 SJ 4.4 10.8 07/12/15 07/17/15 20:01 5:01 EB/WB Begin: Potato Slough
End: Flag City Boulevard
Restriction: One-way traffic control
Reason: Paving Operation
15 mins
26 CAL 9.9 10.3 07/13/15 07/17/15 7:01 17:01 EB/WB Begin: Hogan Dam Road
End: State Route 12
Restriction: One-way traffic control
Reason: Utility Work
5 mins
26 CAL 10 10.5 06/22/15 10/09/15 7:01 5:59 EB/WB Begin: Nove Way
End: State Route 12
Restriction: Long-term #1 of 2 lanes, right shoulder
Reason: Highway Construction
NONE
26 SJ 15.3 20.5 07/14/15 07/14/15 8:30 14:30 EB/WB Begin: Calaveras River
End: San Joaquin/Calaveras County Line
Restriction: One-way traffic control
Reason: Shoulder Work
10 mins
49 AMA 6.1 6.2 07/13/15 07/17/15 8:01 14:30 NB/SB Begin: Jackson Gate Road
End: Depot Road
Restriction: #1, #2 of 2 lanes
Reason: Drainage Cleaning
5 mins
49 AMA 17 17.2 07/12/15 07/12/15 7:01 16:01 NB/SB Begin: Laverone Street
End: Main Street/Plymouth Shenandoah Raod
Restriction: #1 of 2 lanes
Reason: Utility Work
5 mins
49 CAL 10.8 11.7 07/13/15 07/13/15 8:01 14:30 NB/SB Begin: Deer Creek Road
End: Cosgrove Road
Restriction: One-way traffic control
Reason: Shoulder Work
5 mins
49 CAL 11.7 16.4 07/15/15 07/17/15 8:01 14:30 NB/SB Begin: Cosgrove Road
End: Calaveritas Creek
Restriction: One-way traffic control
Reason: Shoulder Work
5 mins
49 MPA 29.4 48.8 07/13/15 07/17/15 5:30 13:01 NB/SB Begin: Bear Valley Road
End: Mariposa/Tuolumne County Line
Restriction: Moving closure – left shoulder, right shoulder
Reason: Maintenance Operation
5 mins
59 MER 23 33.7 07/13/15 07/17/15 6:01 18:01 NB/SB Begin: Oakdale Road
End: La Grange Road
Restriction: One-way traffic control
Reason: Grinding and Paving
10 mins
88 ALP 0 7.8 07/12/15 07/17/15 18:01 6:01 EB/WB Begin: State Route 88
End: East of Forestdale Road
Restriction: #1 of 2 lanes
Reason: Chip Seal Operation
20 mins
88 ALP 0 7.8 07/13/15 07/17/15 6:01 18:01 EB/WB Begin: State Route 88
End: East of Forestdale Road
Restriction: One-way traffic control
Reason: Paving Operation
20 mins
88 AMA 14.5 17.8 07/13/15 07/17/15 8:01 15:01 EB/WB Begin: Pitt Street
End: Previtali Road
Restriction: One-way traffic control
Reason: Shoulder Work
5 mins
88 SJ 6.1 6.1 07/12/15 07/17/15 20:01 7:01 EB/WB Begin: Calaveras River
End: Calaveras River
Restriction: One-way traffic control
Reason: Highway Construction
10 mins
88 SJ 6.1 6.1 07/13/15 07/17/15 9:01 15:01 EB/WB Begin: Calaveras River
End: Calaveras River
Restriction: One-way traffic control
Reason: Highway Construction
10 mins
88 SJ 7.5 7.5 07/06/15 07/17/15 7:01 23:59 EB/WB Begin: Moshier Creek
End: Moshier Creek
Restriction: Long-term one-way traffic control
Reason: Highway Construction
15 mins
88 SJ 9.3 9.3 07/12/15 07/17/15 20:01 7:01 EB/WB Begin: Bear Creek
End: Bear Creek
Restriction: One-way traffic control
Reason: Highway Construction
10 mins
88 SJ 9.3 9.3 07/13/15 07/17/15 9:01 15:01 EB/WB Begin: Bear Creek
End: Bear Creek
Restriction: One-way traffic control
Reason: Highway Construction
10 mins
88 SJ 10.7 9.6 07/13/15 07/14/15 9:01 14:01 EB/WB Begin: Kettleman Lane
End: Harney Lane
Restriction: One-way traffic control
Reason: Tree Work
15 mins
89 ALP 6.5 10 07/13/15 07/17/15 8:30 18:01 NB/SB Begin: Heena Lake Road (Left)
End: Closure Gate
Restriction: One-way traffic control
Reason: Slide Removal
10 mins
89 ALP 10 14.7 07/13/15 07/17/15 8:30 18:01 NB/SB Begin: State Route 4
End: Laramie Street
Restriction: One-way traffic control
Reason: Slide Removal
10 mins
89 ALP 10 24 07/13/15 07/17/15 6:01 18:01 NB/SB Begin: State Route 4
End: Alpine/El Dorado County Line
Restriction: One-way traffic control
Reason: Shoulder Work
15 mins
99 MER 0 0.6 07/15/15 07/16/15 19:01 6:01 SB Begin: Merced/Madera County Line
End: South of Vista Avenue
Restriction: #2, #1 of 3 lanes, left shoulder (alternately)
Reason: Striping Operation
5 mins
99 MER 0.6 4.6 07/13/15 07/17/15 6:01 16:01 SB Begin: South of Vista Avenue
End: Buchanan Hollow Road
Restriction: #1, #3 of 3 lanes, left shoulder, right shoulder
Reason: Shoulder Work
10 mins
99 MER 13.9 13.9 07/15/15 07/16/15 6:01 15:01 NB Begin: State Route 140
End: State Route 140
Restriction: Full connector ramp closure
Reason: Shoulder Work
10 mins
99 MER 14.1 14.1 01/21/15 12/31/15 18:01 17:59 SB Begin: State Route 99
End: East State Route 140
Restriction: Long-term full off-ramp closure
Reason: Highway Construction
5 mins
99 MER 14.4 14.4 01/21/15 12/31/15 18:01 17:59 SB Begin: G Street
End: G Street
Restriction: Long-term full on-ramp closure
Reason: Highway Construction
5 mins
99 MER 14.4 14.4 07/15/15 07/16/15 6:01 15:01 NB Begin: G Street
End: G Street
Restriction: Full off-ramp closure
Reason: Shoulder Work
10 mins
99 MER 18.5 21.6 07/15/15 07/16/15 20:01 4:59 NB Begin: Franklin Road
End: East Atwater Overhead (North of Atwater Boulevard)
Restriction: #2, #1 of 2 lanes
Reason: Highway Construction
10 mins
99 MER 20.4 20.4 10/07/14 10/07/15 20:01 20:01 SB Begin: Route 99
End: Buhach Road Over-Crossing
Restriction: Long-term full off ramp closure
Reason: Highway Construction
10 mins
99 MER 20.4 20.4 10/07/14 10/07/15 20:01 20:01 SB Begin: Buhach Road
End: Buhach Road
Restriction: Long-term full on and off-ramp closure
Reason: Highway Construction
10 mins
99 MER 20.4 20.4 06/16/15 12/31/15 20:01 23:59 NB Begin: Buhach Road
End: Buhach Road
Restriction: Long-term full on and off ramp-closure
Reason: Highway Construction
10 mins
99 MER 20.4 20.4 06/22/15 12/31/15 20:01 23:59 NB Begin: Buhach Road Over-Crossing
End: Route 99
Restriction: Long-term full on ramp closure
Reason: Highway Construction
10 mins
99 MER 21.6 18.5 07/12/15 07/15/15 22:01 4:59 SB Begin: East Atwater Overhead (North of Atwater Boulevard)
End: Franklin Road
Restriction: #2, #1 of 2 lanes (alternately)
Reason: Highway Construction
10 mins
99 MER 31.9 33.5 07/13/15 07/13/15 9:01 14:01 NB Begin: Collier Road
End: South Avenue
Restriction: #2 of 2 lanes
Reason: Pavement Repair
15 mins
99 SJ 6.7 6.7 07/12/15 07/17/15 21:01 6:01 SB Begin: State Route 120/Yosemite Avenue
End: State Route 120/Yosemite Avenue
Restriction: #1 of 2 lanes
Reason: Bridge Work
10 mins
99 SJ 6.7 11.5 07/12/15 07/17/15 20:01 5:01 NB Begin: State Route 120/Yosemite Avenue
End: French Camp
Restriction: #2, #1 of 2 lanes
Reason: Core Drilling
5 mins
99 SJ 6.7 11.5 07/12/15 07/17/15 20:00 5:01 NB/SB Begin: State Route 120/Yosemite Avenue
End: French Camp
Restriction: #1, #2 of 2 lanes
Reason: Core Drilling
5 mins
99 SJ 9.2 14.6 07/12/15 07/17/15 20:01 5:01 NB/SB Begin: Lathrop Road
End: Arch Road
Restriction: #1, #2 of 2 lanes, median, right shoulder, left shoulder
Reason: Core Drilling
10 mins
99 SJ 9.2 14.6 07/13/15 07/17/15 21:01 5:01 SB Begin: Lathrop Road Over-Crossing
End: Arch Road Under-Crossing
Restriction: #1, #2 of 2 lanes, left shoulder, median
Reason: Bridge Work
10 mins
99 SJ 11.5 11.5 07/12/15 07/13/15 20:01 5:01 NB/SB Begin: French Camp Road
End: French Camp Road
Restriction: Full on and off-ramp closure
Reason: Drainage Work
10 mins
99 SJ 11.8 11.8 07/14/15 07/15/15 20:01 5:01 NB Begin: Lone Tree Slough
End: Lone Tree Slough
Restriction: #1, #2 of 2 lanes
Reason: Bridge Work
10 mins
99 SJ 14.6 14.6 07/12/15 07/17/15 21:01 6:01 NB Begin: Arch Road
End: Arch Road
Restriction: #1 of 2 lanes
Reason: Bridge Work
10 mins
99 SJ 14.6 16.7 07/13/15 07/17/15 7:01 17:01 N/A Begin: West Frontage Road NB/SB
End: West Frontage Road NB/SB
Restriction: #2, #1 of 2 lanes (on local cross-street)
Reason: Graffiti Removal
10 mins
99 SJ 14.6 18.7 07/12/15 07/17/15 21:01 5:01 NB Begin: Arch Road
End: State Route 4/Crosstown Freeway
Restriction: #1, #2 of 2 lanes
Reason: Highway Construction
10 mins
99 SJ 16.7 16.7 07/12/15 07/17/15 22:01 5:01 SB Begin: Mariposa Road
End: Mariposa Road
Restriction: Full on-ramp closure
Reason: Highway Construction
10 mins
99 SJ 17.2 17.2 07/12/15 07/17/15 21:01 5:01 NB Begin: Peterson Detour for Mariposa Temporary Ramp
End:Peterson Detour for Mariposa Temporary Ramp
Restriction: Full on-ramp closure
Reason: Highway Construction
10 mins
99 SJ 17.2 17.2 07/12/15 07/17/15 22:01 5:01 SB Begin: East State Route 4/Farmington
End: East StateRoute 4 /Farmington
Restriction: Full off-ramp closure
Reason: Highway Construction
10 mins
99 SJ 17.4 17.4 07/12/15 07/17/15 21:01 5:01 NB Begin: Golend Gate Avenue
End: Golden Gate Avenue
Restriction: Full off-ramp closure
Reason: Highway Construction
10 mins
99 SJ 18.7 14.6 07/12/15 07/17/15 22:01 5:01 SB Begin: State Route 4/Crosstown Freeway
End: Arch Road
Restriction: #2, #1 of 2 lanes
Reason: Highway Construction
10 mins
99 SJ 12.7 16.7 07/13/15 07/17/15 7:01 17:01 N/A Begin: Mariposa West Frontage Road
End: Mariposa West Frontage Road C
Restriction: #2, #1 of 2 lanes (on local street)
Reason: Miscellaneous Work
10 mins
99 SJ 19.3 19.3 07/13/15 07/17/15 7:01 16:01 NB Begin: State Route 26/Fremont
End: State Route 26/Fremont
Restriction: Partial on-ramp closure (left shoulder, right shoulder)
Reason: Shoulder Work
NONE
99 SJ 20.3 20.3 07/13/15 07/17/15 7:01 16:01 NB Begin: State Route 88/Waterloo
End: State Route 88/Waterloo
Restriction: Partial on-ramp closure (right shoulder, left shoulder)
Reason: Shoulder Work
NONE
99 SJ 20.9 20.9 07/13/15 07/17/15 7:01 16:01 NB Begin: Cherokee Road
End: Cherokee Road
Restriction: Partial on-ramp closure (right shoulder, left shoulder)
Reason: Shoulder Work
NONE
99 SJ 22.9 29 07/12/15 07/17/15 19:01 6:01 NB/SB Begin: Hammer Lane
End: South Lodi Overcrossing (South of Kettleman Road)
Restriction: #2, #3, #1 of 3 lanes
Reason: Paving Operation
10 mins
SJ SJ 22.9 29 07/12/15 07/17/15 19:01 6:01 NB/SB Begin: Hammer Lane
End: South Lodi Overcrossing (South of Kettleman Road)
Restriction: Various full off-ramp
Reason: Miscellaneous Work
10 mins
SJ SJ 29 38.8 07/12/15 07/17/15 20:01 5:01 NB Begin: South Lodi Overcrossing (South of Kettleman Road)
End: San Joaquin/Sacramento County Line
Restriction: Various full off/on ramps
Reason: Miscellaneous Work
10 mins
SJ SJ 29 38.8 07/12/15 07/17/15 20:01 6:01 NB Begin: South Lodi Over-Crossing
End: San Joaquin/Sacramento County Line
Restriction: Various full on and off-ramps
Reason: Miscellaneous Work
10 mins
99 SJ 29 38.8 07/12/15 07/17/15 21:00 6:01 NB/SB Begin: South Lodi Overcrossing (South of Kettleman Road)
End: San Joaquin/Sacramento County Line
Restriction: #1 of 2 lanes
Reason: Miscellaneous Work
10 mins
99 SJ 29 38.8 07/12/15 07/17/15 21:00 6:01 SB Begin: South Lodi Over-Crossing
End: San Joaquin/Sacramento County Line
Restriction: #1, #2 of 2 lanes
Reason: Miscellaneous Work
10 mins
99 STA 22.6 22.6 07/13/15 07/17/15 21:01 6:01 SB Begin: Broadway Avenue/ State Route 219
End: Broadway Avenue/ State Route 219
Restriction: Full off-ramp closure
Reason: Paving Operation
10 mins
99 STA 22.6 22.6 07/18/15 07/20/15 20:01 4:00 NB/SB Begin: Broadway Avenue/State Route 219
End: Broadway Avenue/State Route 219
Restriction: Long-term full on and off- ramp closure
Reason: Paving Operation
10 mins
99 STA 22.6 22.6 07/18/15 07/20/15 20:01 4:00 SB Begin: Route 99
End: Broadway Avenue/Route 219
Restriction: Long-term full on ramp closure
Reason: Paving Operation
10 mins
99 STA 15.1 15.1 07/13/15 07/15/15 9:01 14:01 NB Begin: Tuolumne Blvd
End: Tuolumne Blvd
Restriction: Full ramp closure
Reason: Landscape Work
10 mins
99 STA 16.3 16.3 07/13/15 07/15/15 9:01 14:01 NB Begin: 6th and L Street
End: 6th and L Street
Restriction: Full ramp closure
Reason: Landscape Work
10 mins
99 STA 16.8 16.8 07/15/15 07/16/15 9:01 14:01 NB Begin: Kansas Avenue
End: Kansas Avenue
Restriction: Full on and off-ramp closure
Reason: Landscape Work
10 mins
120 SJ 16.5 17.6 07/14/15 07/15/15 19:01 6:01 WB Begin: Irwin Street
End: East Brayton Avenue
Restriction: #1 2 lane
Reason: Striping Operation
10 mins
120 SJ 16.5 17.6 07/14/15 07/17/15 19:01 6:01 EB/WB Begin: Irwin Street
End: East Brayton Avenue
Restriction: #1 of 2 lanes
Reason: Striping Operation
10 mins
132 SJ 3.2 3.2 07/12/15 07/13/15 20:01 6:01 EB/WB Begin: Interstate 5
End: Interstate 5
Restriction: Various Full connector ramp closure
Reason: Pavement Repair
10 mins
132 STA 1.43 2.435 07/13/15 10/16/15 8:01 16:01 EB/WB Begin: West of Bird Road
End: Kasson Road
Restriction: One-way traffic control
Reason: Misc Maintenance work
15 mins
132 STA 15.1 15.1 07/13/15 10/16/15 6:01 23:59 WB Begin: 11th Street/D Street
End: 11th Street/D Street
Restriction: Long-term Left Turn Lane
Reason: Traffic Signal Work
5 mins
132 STA 16.1 16.1 07/13/15 07/18/15 7:01 18:01 EB/WB Begin: Santa Ana Avenue
End: Santa Ana Avenue
Restriction: Median/Left Turn Lane
Reason: Utility Work
5 mins
140 MPA 40.5 43.2 03/30/15 12/31/15 6:01 18:01 EB/WB Begin: Savage Trading Post
End: South Fork Merced River
Restriction: Long-term Right Shoulder|Left Shoulder
Reason: Slide Removal
10 mins
152 MER 11.5 13.8 07/12/15 07/18/15 20:01 4:30 EB Begin: San Luis Drive
End: Interstate 5
Restriction: #2 of 2 lanes
Reason: Bridge Work
10 mins
205 SJ 0 13.4 07/13/15 07/16/15 7:01 13:01 EB/WB Begin: Alameda/San Joaquin County Line
End: State Route 205
Restriction: Moving closure – #1 of 3 lanes
Reason: Sweeping Operation
NONE
205 SJ 2.9 13.1 07/12/15 07/17/15 20:01 4:01 WB Begin: 11th Street
End: Paradise Cut
Restriction: #1,#2 of 3 lanes
Reason: Striping Operation
10 mins
205 SJ 2.9 13.1 07/12/15 07/13/15 22:01 10:01 EB Begin: 11th Street
End: Paradise Cut
Restriction: #1,#2 of 3 lanes
Reason: Striping Operation
10 mins
205 SJ 9.6 9.6 07/12/15 07/17/15 19:01 4:01 NB/SB Begin: Paradise Road
End: Paradise Road
Restriction: One-way traffic control
Reason: Bridge Work
10 mins
219 STA 0.1 1.9 07/12/15 07/17/15 21:01 8:01 EB/WB Begin: State Route 219
End: East of Dale Rd
Restriction: #2 of 2 lanes
Reason: Utility Work
10 mins
219 STA 0 1.9 07/18/15 07/20/15 20:01 4:00 EB/WB Begin: Sisk Road
End: Salida Blvd
Restriction: Full Hwy closure
Reason: Paving Operation
10 mins